1. Project Background
Saudi Aramco's Jafurah is the largest unconventional (shale) gas play in the Middle East. The field sits in the Eastern Province of Saudi Arabia and is the linchpin of the kingdom's domestic-gas pivot — replacing oil burned for power generation with gas, freeing up crude for export and petrochemicals.
Public reporting from Aramco and industry press (JPT, MEED, Offshore Technology) puts the field's reserves at approximately 229 trillion cubic feet of raw gas plus 75 billion stock-tank barrels of condensate.
In parallel with Jafurah, Aramco is executing Master Gas System Phase 3 — a country-wide pipeline network expansion designed to move the new gas to demand centres.
2. Scale by the Numbers
From the June/July 2024 award round (Aramco's "Strategic Gas Expansion" announcement):
| Metric | Public figure |
|---|---|
| Total contract value (2024 round) | ~ US$ 25 bn |
| Jafurah Phase 2 EPC awards | 16 contracts, ~ US$ 12.4 bn |
| Master Gas System Phase 3 awards | US$ 8.8 bn across 15 LSTK contracts |
| MGS Phase 3 new pipeline length | 821 km |
| 2028 cumulative MGS expansion target | ~ 4,000 km of new pipelines, 17 new compression trains, +3.15 Bscf/d capacity |
| Jafurah surface network | ~ 1,500 km of transfer / gathering / flowlines |
| Target Jafurah production | 2 Bcf/d by 2030; first gas expected 2025 |
EPC packages publicly named:
- Package 1 (gas processing plant): Larsen & Toubro Energy Hydrocarbon — ~ $2.9 bn
- Package 2 (utilities/offsites): Hyundai Engineering — ~ $2.4 bn
- Package 3 (gas compression units): Larsen & Toubro — ~ $1 bn
- Jafurah Phase 3 EPC (LOA Sep 2024): Técnicas Reunidas / Sinopec consortium, ~ US$ 2.24 bn for additional gas-compression plants
- MGS Phase 3 line-pipe Packages 6 & 7 (later 2024): Sinopec Oil Engineering & Construction, ~ US$ 1.4 bn
3. Fittings & Standards Profile of an EPC Package This Size
Based on what large EPC packages of this nature typically specify in their public bid documents (not project-specific BOM):
- NACE MR0175 / ISO 15156-3 sour-service compliance is the default for upstream Jafurah piping
- ASME B16.9 buttweld fittings in carbon and low-alloy grades
- ASME B16.5 (NPS ≤ 24) and B16.47 (NPS ≥ 26) Series A flanges
- API 6A wellhead spools and tree connections
- MSS SP-75 WPHY 60-70 grades for high-yield transmission segments
- Large-bore induction bends (≥ DN 600) for cross-country lines
- Duplex / super-duplex transitions for high-H₂S sour gas service
- Low-temperature carbon steel (A420 WPL6 or equivalent) for refrigerated processing trains
EPCs typically require EN 10204 type 3.1 mill test certificates, with type 3.2 (independent inspector) for high-pressure or sour-service items.
4. Supply-Chain Challenges
Three megaprojects running simultaneously — Jafurah, Master Gas Phase 3, and the ongoing Fadhili expansion — have created supply-chain tightness across the long-lead-time fittings categories:
- Forging slot capacity: Lead times for large-OD forged flanges and high-yield WPHY induction bends have reportedly stretched to 30-50 weeks at Tier-1 mills
- Vendor approval: SAP-Aramco (Saudi Aramco Project Vendor Program) approval typically takes 12-18 months and is now the gating step for any new manufacturer
- NACE-compliant heat treatment: Plants set up for normalised + tempered heats are running at full utilisation
- Documentation throughput: Independent third-party inspection (SGS, BV, TÜV, DNV) on every NACE batch slows delivery cycles
5. Lessons for International Buyers and EPC Procurement Teams
For EPC contractors and trading houses watching the next wave of awards:
- Reserve forging slots early — for any project starting after Q4 2025, forged-flange and induction-bend slots booked in 2024 are already committed
- Dual-source qualification is no longer optional on critical items
- Document every step — full traceability (heat → MTC → NDT report → packing → site receipt) is being audited more aggressively by Aramco PMTs
- Vendor approval preparation matters — manufacturers eyeing Saudi mega-projects should start their SAP-Aramco filing now; it is a 12-18-month track
- NACE compliance proof is increasingly verified at first-article + random-lot witness level, not just paperwork
6. Reference Takeaway
The remaining packages (Jafurah Phase 3 utilities, additional MGS Phase 3 segments, downstream connections) are likely to lock in additional fittings demand through 2028. Industry watchers should monitor:
- MEED Projects database for upcoming awards
- Aramco's quarterly results for capex pacing
- JPT / Pipeline & Gas Journal for technical scope updates
This article is provided as an industry reference for international buyers and trading houses to understand the procurement pipeline shape. Hebei Haihao does not claim involvement in any project named.
Sources: Saudi Aramco corporate releases, Journal of Petroleum Technology (SPE), MEED, Offshore Technology, Tecnicas Reunidas / Sinopec / Hyundai Engineering / L&T public announcements.
Related Products
For physical supply of the specs discussed above, refer to the relevant Hebei Haihao product categories:
Or browse the full product catalogue and filter by ASTM / ASME / EN / GB standards, material grades, and size ranges.
Further Reading
Next Steps
- This article is a procurement reference; all standard numbers, chemistry limits, and process parameters defer to the latest published edition
- For project RFQs, submit your specs via the inquiry form; we respond within 4 business hours
- Factory certifications and inspection capability are listed on the certificates page
Behöver du en offert för produkterna i denna artikel?
Skicka dina specifikationer så svarar vårt tryckrörsteam inom en arbetsdag.
Skicka RFQVidare läsning
FallstudierQatarEnergy NFE: Efterfrågan på kryogena rördelar för LNG
Branschreferensfall baserat på offentliga tillkännagivanden från EPC-entreprenörer. Världens största enskilda LNG-utbyggnad skapar en flerårig inköpspipeline för kryogena 9% Ni- och rostfria rördelar.